Hammerson House Progress
Hammerson House Progress
03 May 2019
Great to see the latest progress for this new residential care scheme in London. It's Week 32 and the Level 2 columns are nearly complete. Shuttering for Level 3 slab will start next week.
P+HS Architects is working with Bowmer & Kirkland and Nightingale Hammerson on the development which is due for completion in 2020. This fabulous project will provide a world class 116 bed residential centre for the Jewish Community. Read more here.