On Site Hammerson House

IMG 7323

On Site Hammerson House

Work has now started on a new Hammerson House to create a world-class 116 bed residential centre for the Jewish community. The new building will be organised around small clusters of bedrooms with their own facilities such as a lounge and kitchen to make it feel really like a ‘home from home’.



https://nightingalehammerson.org/hammerson-redevelopment



19th September 2019

Week 47

Steel roof structure erected, ready to receive timber rafters and tiles. Underfloor heating progressing well and household corridors taking shape. Basement tanking complete ready for screed finish.

HH 15
HH 14
HH 09
HH 13
HH 10
HH 12
HH 11

blank

15th August 2019

Visit to site today showed progress on, commencement of basement tanking, drainage layer and perimeter drain installation, waterproofing, insulation and ballast complete to northwest corner of roof. The steel roof structure is due to commence in September.

HH 07
HH 08

Erection of internal walls is progressing to form Level 2, and SFS installation complete up to Level 3. Level 2 brickwork to due commence early next week.

HH 09
HH 010
HH 011

blank

June 2019

Week 34

Concrete frame progressing well. Level 4 shuttering nearing completion ready for concrete pour, next week.

IMG 7323

blank

June 2019

Week 32

Level 2 columns nearly complete. Shuttering for Level 3 slab to commence next week.

IMG 7134

blank

April 2019


Progressing with RC frame. Basement floor and walls complete. Ground floor slab and lift cores progressing well. Shuttering for first floor column has commenced, ready for pour, next week.

IMG 6986
IMG 6975

Key People