On Site Hammerson House

IMG 7323

On Site Hammerson House

A new 116 bed care home for Nightingale Hammerson.


https://nightingalehammerson.org/hammerson-redevelopment



September 2020

IMG 0313
IMG 0354
IMG 0346

blank

June 2020

The tower crane has gone and most of the scaffolding removed with just some remaining around the main entrance. Landscaping works are taking shape outside. Internally, fittings and doors are being installed and tiling and floor finishes are underway.

blank

January 2020

Roofing works underway with a view from the tower crane

2961 Jan 20 Roofing IMG 20200117 WA0020

blank

October 2019

Images taken from the tower crane.

IMG 20191106 WA0028
IMG 20191106 WA0025
IMG 20191106 WA0026

blank

19th September 2019

Week 47

Steel roof structure erected, ready to receive timber rafters and tiles. Underfloor heating progressing well and household corridors taking shape. Basement tanking complete ready for screed finish.

HH 15
HH 14
HH 09
HH 13
HH 10
HH 12
HH 11

blank

15th August 2019

Visit to site today showed progress on, commencement of basement tanking, drainage layer and perimeter drain installation, waterproofing, insulation and ballast complete to northwest corner of roof. The steel roof structure is due to commence in September.

HH 07
HH 08

Erection of internal walls is progressing to form Level 2, and SFS installation complete up to Level 3. Level 2 brickwork to due commence early next week.

HH 09
HH 010
HH 011

blank

June 2019

Week 34

Concrete frame progressing well. Level 4 shuttering nearing completion ready for concrete pour, next week.

IMG 7323

blank

June 2019

Week 32

Level 2 columns nearly complete. Shuttering for Level 3 slab to commence next week.

IMG 7134

blank

April 2019


Progressing with RC frame. Basement floor and walls complete. Ground floor slab and lift cores progressing well. Shuttering for first floor column has commenced, ready for pour, next week.

IMG 6986
IMG 6975

Key People