On Site HASU Cumbria infirmary

DSC6271

On Site HASU Cumbria infirmary

A refurb/Refit project for the HASU (Highly Acute Stroke Unit) at Cumbria Infirmary due to be complete the beginning of September. The new ward will provide: reception, 10 beds (2 x 4-bed bays and 2 x single bays), dirty and clean utility, staff bases and storage. The team work to complete the entire ward reconfig/refurb whilst the ward is live, occupied with high acuity patients.

8th August 2019

Work is progressing well on site all of the major alteration elements are now complete, and Mechanical and Electrical installations are nearing completion.

Fixtures and fittings to the utility area are almost finished, and new flooring was being installed.

Client has asked for some additional doors and some changes to storage solutions which have now been incorporated into the scheme.

Works are due for completion on 30 August 2019

DSC6264