On Site Hydrotherapy Pool

3368 Hydrotherapy Plan

On Site Hydrotherapy Pool

We are working on two schemes for the PCP (Pioneering Care Partnership): a new Hydrotherapy Pool and an extension to their Options Room. Located at the Pioneering Care Centre in Newton Aycliffe, County Durham, the PCP’s Hydrotherapy pool is one of the region’s only self-referral fully accessible community pools of its type. Offering over 17,000 appointments annually, the hydrotherapy pool has benefited countless individuals over its 25 years, but had become oversubscribed and outdated, necessitating a complete overhaul. P+HS Architects have been working closely with the charity and contractor MGM Construction to redevelop the pool, doubling capacity, and ensuring that it meets modern standards allowing more people to benefit from its state-of-the-art facilities for years to come. We are also providing an extension to the Options Room, a multipurpose activity space used by a range of people with varying needs. The new facilities will allow the service better capacity to deliver the first-class sessions that members love, which promote independence and social inclusion. As well as increasing the space, the new extension will provide a new kitchen area and access outdoors to a communal garden and seating area.

June 2024

The new hydrotherapy pool at the Pioneering Care Centre , Newton Aycliffe is coming together well.

3368 Hydrotherapy Pool 3

May 2024

A glimpse inside the hydrotherapy pool, with the roof now nearing completion!

3368 PCP Onsite May 2024 2
3368 PCP Onsite May 2024 1

April 2024

Exciting progress is being made at the PCP site, with the latest developments coming along nicely.

March 2024

Rain has made an early attempt to fill the pool, but thanks to the exceptional work by all involved, it has been kept at bay.

3368 PCP Onsite March 2024 3
3368 PCP Onsite March 2024 2

February 2024

The slab has been successfully laid for the hydrotherapy pool. Meanwhile, the Options Room extension is advancing rapidly, with the roof in place with the windows and doors ready to be fitted next.

January 2024

The site gives a real sense of the size of the new redevelopments at the PCP. The existing pool extends to the demolished wall on the left, while the expansion area is marked by the newly laid foundations.

3368 PCP Onsite Jan 2024 2
3368 PCP Onsite Jan 2024 1

2023

The 20 year old hydrotherapy pool before undergoing redevelopment.

PCP Hydrotherapy Pool Before blurred face

Key People